60%

Reduced commissioning time

30%

Reduced commissioning cost

BACKGROUND

A SPM manufacturer faced challenges in meeting tight delivery schedules due to long on-site commissioning and frequent design iterations.

CHALLENGE

  • Late discovery of control logic issues
  • Long on-site commissioning and test time
  • High cost due to rework and machine downtime
  • Difficulty in validating machine performance before physical build

APPROACH

  • Create accurate 3D model of machine in digital twin environment
  • Integrate PLC program, HMI, and field I/O virtually
  • Run machine sequences, test interlocks, alarms, and safety logic
  • Virtual Commissioning Complete
  • Validated system ready for on-site deployment

40% improvement in production efficiency

35% reduction in cycle time

30% reduction in product wastage

45% reduction in manual intervention

Improved filling accuracy and cap sealing consistency

Enhanced machine reliability and throughput